PCI-1Project: Pickaway Correctional Institution
Client: Ohio Department of Rehabilitation & Corrections
Location: Orient, Ohio
Completed: 2015

M-Engineering provided design and construction administration services for two new 2500 KW generators housed in a new addition to the existing power plant facility. A new 10,000 gallon fuel storage tank was also designed and installed. A new underground 13.2V cable distribution system to new transformers located outside the perimeter security fence replaced the existing underground system within the perimeter security fence. Existing generators and transformers located within the security fence were removed. The project reused all existing building electrical panels and building electrical distributions systems.

Project Type: Institutional
Cost: $9,200,000
Area/Size: N/A
Services Provided: HVAC System, Electrical, Structural, Fire protection and Construction Administration